The Audit Court criticizes the Board again and advises a capital increase. The personal consequences may be tougher than expected yet.

Audit Court: Capital Increase for Vienna Airport / Picture: © Vienna Airport / Flughafen Wien AG

The new major terminal under construction at the Vienna Airport, project "Skylink", provides for further internal political conflicts. The terminal exceeds by far the originally projected cost of € 402 million with the currently expected cost of over € 952 million.

Recently, Vienna's Mayor Michael Häupl called for personal consequences. That the responsible CEO Herbert…